Evaluation of Progress, Steps Needed to Finish: Part 13
"How do you eat an elephant?"

Green lettering---Green House, Yellow Lettering---Shop
Warning: Greenhouse door also doubles as time portal, be sure to close after use, see picture below...

  STEP NEEDED FOR EST/ACT TIME EST/ACT COST OK DONE
1 Install Electrical Power Shop, constuction, GH 2 weeks/1 week $150/150 X July 2, 2009
2 Install GH Door Frame planning 2 days/2 days+ $150/150 X July 5,2009
3A *Install Aluminum GH Frame lower Glazing Support/frame 2 wks /3month $300/$700 X October 29, 2009
3B ends Ends + Vents 3 wks $500/$200 X June 2010
3C upper Roof 1 wk/1 month $300/$300   August 2010
4 Install GH Glazing lower Environmental Control 1 wk $500/infin. X August 2010
  Install GH Glazing upper " " ? $500/$500 -- pending
5 Install Water Supply " " 2 wks $500/$1300bid    
6 Panel saw and router jig to install walls in shop 1 day / 1 month! $0/$80 X August 18, 2009
7 Buy Table Saw and benches projects and etc. 1 day $900    
8 Install shop walls/ceiling not needed but nice 3 wks $0    
8A Install cabinets shop tool storage, protect ?? ??    
8B Install cabinets lab lab storage, protect ?? ??    
9 Install GH Lights E. Controls 1 wk $200    
10 Install watering/heater controls E. Controls 1 wk $200    
11 Ceiling insulation to keep warm/cold 1 day ????$1000    
12 Install shop lights Improve shop use .. 2 hrs $0-50 X July 8, 2009
13 Install lab lights Improve lab use .. 2 hrs/2 hrs $0/0 X July 7, 2009
14 Install storage area lights Darn good question 2 hrs $0-50 X July 12, 2009
15 Shelving & benches frm OH storage & workspace 4-5 hrs $0    
16 Desks from Old House (OH) workspace 3-5 hrs $0    
17 Move bldg. mat. to barn improve workspace 3-5 hrs $0   July 2010
18 Pressure wash, clean floor improve workspace 3-5 hrs 0-$150    

To any former students, according to most industrial operations books the path to maximum productivity (thank you George Danzig) is to
do the easiest, shortest jobs first, exactly opposite what your mom told you to do. These tend to yield quickest, yield greatest profit, use up the
least materials, clear the most from your docket, make the most customers happy, clean up the shop floor, and pave the way to the more difficult
tasks by building capability. It may also be the reason I never get my greenhouse built. Could mom have been right after all??

#1 - Electricity #2 - GH Door #1 - REMC Gophers
#3-lower shell #6-panel saw  
     
     
     

 

July estimated cost to finish greenhouse is about $2000 and 7 weeks labor. Estimated cost to finish shop wais about $1700 and 4 weeks labor. The panel saw was a bad surprise. I broke out in hives about July 15 and still have the little buggers, I didn't realize how many measurements and screw sizes would hold up that project. I finally gave up on mounting pillow blocks at the base and bought a $4.50 piece of oak from Holmes lumber that I used to make two stop blocks. This means the saw won't fall out on my foot and it means the height is set where I want, not where it happened to show up. If I decide to document the panel saw you will see the pain involved, at least 20 different length and type of screws each purchased individually with a corresponding trip to town!! . Since it was on the critical path for both the greenhouse and shop, it really messed things up. Cut the uprights for the gh walls August 1. This meant: A. Chop saw cutting scheme for 2" aluminum works, yea. It also means I am now stuck with a wall height of 32-34 inches. If I chose 32, I can cut polycarbonate panes in 3 pieces but I lose light, I am drifting toward 34, hmm, thats a lot of patching but the appearance and light are better. Last entry August 18, 2009, panel saw marginally usable.

* See page 14 for thousand pound gorilla.

Part13.html
This page created by Edward A. Kimble
Last modified 0208/18/2009